Numerous deep potholes

Reported via iOS in the Potholes / Highway Condition category anonymously at 15:37, Thursday 29 January 2026

Sent to West Northamptonshire Council less than a minute later. FixMyStreet ref: 8796228.

These potholes getting worse and worse. Length of road between Lilac Cottage and Ladycroft. This is in unlit road, perilous and dangerous for pedestrians at night

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 15:37, Thursday 29 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.

    Posted by West Northamptonshire Council at 19:29, Monday 2 February 2026

  • Still open, via questionnaire, 18:37, Thursday 26 February 2026

  • 55 days, what a joke - meanwhile the road deteriorates at an alarming rate

    Posted anonymously at 19:25, Thursday 26 March 2026
    Still open, via questionnaire

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have already been made aware of this issue. A works order has been raised which you can follow on FMS-8796228-1 The expected completion date for these works will be 03/08/26.
    West Northamptonshire Council is committed to maintaining safe and reliable roads, but it isn’t possible to repair every pothole immediately. The council must prioritise repairs based on available budget, workforce capacity, and the need to address the most safety critical defects first. All decisions are guided by the Highway Inspection Manual, which sets out how road defects are assessed and the timescales for repair. This ensures that resources are used responsibly and that the highest risk issues, such as those posing a danger to road users, are dealt with as quickly as possible while lower risk defects are scheduled appropriately within the limits of available funding.

    Posted by West Northamptonshire Council at 14:27, Thursday 2 April 2026

  • Holes are progressively spreading and getting worse

    Posted anonymously at 06:59, Friday 24 April 2026
    Still open, via questionnaire

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have already been made aware of this issue. A works order has been raised which you can follow on FMS-8796228-1 The expected completion date for these works will be 03/08/26.
    West Northamptonshire Council is committed to maintaining safe and reliable roads, but it isn’t possible to repair every pothole immediately. The council must prioritise repairs based on available budget, workforce capacity, and the need to address the most safety critical defects first. All decisions are guided by the Highway Inspection Manual, which sets out how road defects are assessed and the timescales for repair. This ensures that resources are used responsibly and that the highest risk issues, such as those posing a danger to road users, are dealt with as quickly as possible while lower risk defects are scheduled appropriately within the limits of available funding.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 08:15, Friday 24 April 2026

  • Still open, via questionnaire, 12:57, Friday 22 May 2026

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 07:27, Wednesday 27 May 2026

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by West Northamptonshire Council at 14:37, Friday 29 May 2026

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 09:48, Friday 5 June 2026