41D1, 20T39 & 67C1 all 3 lights near me are not working I live at 189 Tubbenden Lane

Reported via mobile in the Light Not Working category anonymously at 14:46, Thursday 29 January 2026 using FixMyStreet Pro ; (there is no pin shown as the user did not use the map)

Sent to Bromley Council less than a minute later. FixMyStreet ref: 8795751.

Ref: 8782991 All 3 lights near a bus stop, have not being working for weeks. I live at 189 Tubbenden Lane.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 14:47, Thursday 29 January 2026

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 07:48, Friday 30 January 2026

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 14:06, Wednesday 4 February 2026

  • Our contractor has been notified to take the appropriate action.

    State changed to: In progress

    Posted by Bromley Council at 12:44, Thursday 5 February 2026

  • Apologies for the delay, we are currently waiting for delivery of materials to enable us to fix the problem.

    Posted by Bromley Council at 11:55, Thursday 9 April 2026

  • We have investigated and identified there is an issue with the electricity supply for this asset. Bromley Council have contacted UK Power Networks and asked them to schedule works to restore this fault.

    Posted by Bromley Council at 11:17, Tuesday 2 June 2026

  • Resident called to chase report, this is still an issue 1 of the lights still needs repairing, please can this be chased with UK Power Network and resident contacted with an update as to when this will be fixed.

    Posted anonymously at 16:00, Wednesday 17 June 2026

  • Works are programmed for the 24 June 2026 from UKPN. Thank you for your patience.

    Posted by Bromley Council at 12:49, Thursday 18 June 2026