LBB Pathway Steps need repainting
Reported via desktop in the Pavement Defect category anonymously at 14:28, Wednesday 28 January 2026
Sent to Bromley Council less than a minute later. FixMyStreet ref: 8787951.
In this area are small steps previously painted by LBB yellow. However over time they have worn away and need repainting.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 14:29, Wednesday 28 January 2026
-
We are continuing to investigate and working to resolve this report
Posted by Bromley Council
at 14:34, Tuesday 3 February 2026
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 12:59, Monday 9 February 2026
-
These works remain outstanding with our contractor, thank you for your continued patience in the meantime.
Posted by Bromley Council
at 11:00, Wednesday 10 June 2026
Only the original reporter may leave updates. If you made the original report please log in to leave an update.