Potholes on two speed cushions

Reported via desktop in the Damaged Speed Humps category anonymously at 13:36, Thu 4 September 2025 using FixMyStreet Pro

Sent to West Northamptonshire Council less than a minute later. FixMyStreet ref: 8118992.

Please can repairs be carried out to two potholes on two speed cushions on Standens Barn Road. The first is on the cushion closest to Cottagewell Court and the other is on the cushion closest to the junction with Billing Brook Road. Many thanks

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 13:36, Thu 4 September 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.

    Posted by West Northamptonshire Council at 08:31, Fri 5 September 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 12:41, Tue 21 October 2025

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by West Northamptonshire Council at 14:40, Mon 10 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 11:25, Tue 11 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by West Northamptonshire Council at 11:40, Wed 19 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 12:11, Wed 19 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 13:24, Fri 21 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 13:58, Fri 21 November 2025