Fixed
Lines faded
Reported via Android in the Road Markings - Worn/Faded category anonymously at 10:50, Thu 4 September 2025
Sent to West Northamptonshire Council less than a minute later. FixMyStreet ref: 8117785.
Lines need repainting
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 10:50, Thu 4 September 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.
Posted by West Northamptonshire Council at 07:25, Fri 5 September 2025
-
I have witnessed this evening a car travelling from Kilworth road through these bollards on to Weston hall lane, I did tell the builders at the time that the bollards weren’t close enough and I was told they were dealing with it, but they never did, this is not supposed to be a through road
Posted anonymously at 18:10, Tue 23 September 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 07:04, Wed 24 September 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 15:17, Wed 3 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 23:50, Wed 3 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 00:56, Thu 4 December 2025
This report is now closed to updates from the public. You can make a new report in the same location.