Blocked Drain Backing Up

Reported via desktop in the Blocked/Damaged category anonymously at 22:56, Wed 3 September 2025

Sent to West Northamptonshire Council 1 minute later. FixMyStreet ref: 8116191.

The drain at the end of High Street at the T-Junction with the A5 is very badly blocked causing water to back up and form very large puddles at the edge of the road.

The verge has also been eroded away and damaged and there are multiple deep potholes around the drain which means it is raised up with it's ironwork edges displaying.

Drain needs vacuum sucking and then the road surface needs repair with kerb stones installed to rebuild the verge and stop it from collapsing again.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 22:57, Wed 3 September 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A Community Steward has assessed the photo/s and we can confirm that the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.

    Posted by West Northamptonshire Council at 08:30, Thu 4 September 2025

  • Caller advised this report has still not been done and still requires investigation as no update has been given since as of yet.

    Posted anonymously at 15:27, Thursday 5 February 2026

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A Community Steward has assessed the photo/s and we can confirm that the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 07:40, Monday 9 February 2026

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 11:08, Monday 23 March 2026

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 10:22, Wednesday 6 May 2026

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Investigating

    Posted by West Northamptonshire Council at 18:00, Friday 15 May 2026

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 12:36, Monday 18 May 2026