Fixed
Middle section of foot bridge is rotting
Reported via mobile in the Bridge-Damaged/ Missing category anonymously at 17:22, Sun 17 August 2025
Sent to West Northamptonshire Council less than a minute later. FixMyStreet ref: 8036843.
Middle section has a large crack and moves a lot when you put weight on it, it will soon break
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 17:22, Sun 17 August 2025
-
Investigation: Ongoing - Thank you for your enquiry. A qualified Highways Inspector has assessed the location, and we are undertaking a landownership investigation and will update you shortly.
Posted by West Northamptonshire Council at 14:49, Mon 18 August 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.
Posted by West Northamptonshire Council at 15:47, Wed 20 August 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 07:35, Thu 2 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 12:26, Thu 2 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 15:24, Thu 2 October 2025
This report is now closed to updates from the public. You can make a new report in the same location.