Fixed
RE: Uneven footpath
Reported via mobile in the Slabs - Uneven / Damaged / Cracked category by Craig Blacha at 18:13, Wed 30 July 2025
Sent to West Northamptonshire Council less than a minute later. FixMyStreet ref: 7956393.
Uneven footpath as seen in image large drop from cracking
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 18:13, Wed 30 July 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 52 days.
Posted by West Northamptonshire Council at 14:31, Fri 1 August 2025
-
Investigation: Ongoing (Defect Found), Defect Repair: Not Started - Thank you for your enquiry, and please accept our apologies for the delay in completing this work. We are currently prioritising urgent safety‑related defects, which has caused some rescheduling.
These works have now been rearranged for 12th March.
Posted by West Northamptonshire Council at 13:13, Thursday 29 January 2026
-
Investigation: Ongoing (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 10:20, Friday 6 March 2026
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Scheduled - We can confirm that we have already been made aware of this issue. A works order has been raised which you can follow on 7956393 and add updates. The expected completion date for these works will be 12/3/26.
Posted by West Northamptonshire Council at 14:19, Friday 6 March 2026
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 20:40, Thursday 12 March 2026
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 22:58, Friday 13 March 2026
This report is now closed to updates from the public. You can make a new report in the same location.