You can move around with your keyboard
plus
minus
left
right
Drop pin on the map to start a new report
space
Press space again to adjust the location
space
Start new report here Reposition report here
Back to all reports

Road damaged

Reported via desktop in the Road Defect category anonymously at 11:52, Fri 16 May 2025 using FixMyStreet Pro

Sent to Bromley Council less than a minute later. FixMyStreet ref: 7578551.

Road damaged on zebra crossing as road has been damaged by the heavy buses going up and down

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 11:54, Fri 16 May 2025

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 11:54, Mon 19 May 2025

  • A job has been raised but Traffic Managent has to be arranged to carry out this work safely. Thank you for your patience.

    Posted by Bromley Council at 10:29, Tue 1 July 2025

  • Our contractor is aware this repair is outstanding. Thank you for your patience.

    Posted by Bromley Council at 18:05, Tue 22 July 2025

  • We are working with our contractor to ensure works are completed. Thank you for your patience.

    Posted by Bromley Council at 18:07, Tue 29 July 2025

  • Thank you for your patience. We are working with our contractor to ensure this work gets completed.

    Posted by Bromley Council at 10:18, Thu 31 July 2025

  • We are waiting for Traffic Management to be agreed so that the work can commence. Thank you for your patience.

    Posted by Bromley Council at 11:12, Tue 5 August 2025

  • Traffic management is being sorted. Thank you for your patience.

    Posted by Bromley Council at 13:21, Thu 7 August 2025

  • Our contractor is arranging a bus diversion to carry out the works safely. Thank you for your patience.

    Posted by Bromley Council at 12:05, Thu 21 August 2025

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 15:06, Fri 22 August 2025

  • Our contractor has chased the outstanding road markings. Thank you for your patience.

    Posted by Bromley Council at 16:46, Tue 2 September 2025

  • We can confirm that a contractor will be attending to carry out the necessary repairs. These works have been scheduled and will be completed in due course as part of our maintenance programme.

    Posted by Bromley Council at 14:09, Fri 5 September 2025

  • We are just waiting for our contractor to complete the road markings. Thank you for your patience.

    Posted by Bromley Council at 11:34, Wed 24 September 2025

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 11:31, Mon 27 October 2025

This report is now closed to updates from the public. You can make a new report in the same location.