Failed Kerb Repair

Reported via desktop in the Damaged/Loose category by Jake Ledger at 04:29, Thursday 13 February 2025 using FixMyStreet Pro

Sent to West Northamptonshire Council less than a minute later. FixMyStreet ref: 7127109.

Recent repair to the uneven reinstated kerb outside number 105 Welford Road has failed. Leaving the stone vertically displaced under the adjacent kerbing by approximately 30mm.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 04:29, Thursday 13 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 55.5 days.

    Posted by West Northamptonshire Council at 13:25, Thursday 13 February 2025

  • Please confirm if this repair has been ordered under P3, as it should be following WNC's inspection manual.

    Posted by Jake Ledger at 17:03, Thursday 13 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 18.5 days.

    Posted by West Northamptonshire Council at 09:52, Tuesday 18 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 09:27, Monday 24 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 08:41, Tuesday 25 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 08:55, Tuesday 25 February 2025

This report is now closed to updates from the public. You can make a new report in the same location.