Action scheduled
Finishing the job
Reported via mobile in the Other Road Issues category anonymously at 18:36, Fri 22 November 2024
Sent to Hampshire County Council less than a minute later. FixMyStreet ref: 6772718.
When will the signs between Up Green and Hall Lane advising work in October be removed. Also when is the job to be finished (low ironwork).
Updates
-
State changed to: In progress
Updated by Hampshire County Council at 12:16, Mon 25 November 2024
-
State changed to: Open
Updated by Hampshire County Council at 14:43, Wed 27 November 2024
-
State changed to: Action scheduled
Updated by Hampshire County Council at 14:51, Wed 27 November 2024
-
State changed to: Fixed
Updated by Hampshire County Council at 14:55, Tue 17 December 2024
-
This is NOT fixed. Signage still blights the end of Green Lane onto Firgrove Road, i've nit checked at the end of the Link. Why are highways incapable of clearing up after a job. Also all the drains are now low and a hazard to cyclists and car wheels.
Posted anonymously at 13:04, Wed 18 December 2024
-
State changed to: In progress
Updated by Hampshire County Council at 13:29, Wed 18 December 2024
-
State changed to: Action scheduled
Updated by Hampshire County Council at 16:28, Wed 18 December 2024
-
Action scheduled does NOT answer the question. When will the abandoned signage be removed (YTC has removed the one on the Link) and when is the work scheduled for.
Posted anonymously at 17:20, Wed 18 December 2024
-
State changed to: In progress
Updated by Hampshire County Council at 08:39, Thu 19 December 2024
-
Some signs still not removed and low drains continue to be a hazard
Posted anonymously at 19:17, Fri 20 December 2024
Still open, via questionnaire -
State changed to: Action scheduled
Updated by Hampshire County Council at 09:07, Mon 23 December 2024
-
As already stated, action scheduled does NOT answer the question. Also why is it beyond highways ability to remove signs, sand bags etc when a job is completed.
Posted anonymously at 11:03, Mon 23 December 2024
-
State changed to: In progress
Updated by Hampshire County Council at 11:15, Mon 23 December 2024
-
It is evident that highways will not answer the question
Posted anonymously at 14:17, Mon 23 December 2024
-
State changed to: Closed
Updated by Hampshire County Council at 16:46, Mon 23 December 2024
-
The case is not closed as the work is not done. WHEN are the low ironworks being done. I've received a direct email from Hampshire which, again, ignores this entirely and says the signage, which should have been gathered at the end of the job will be collected at some unknown point in the future. The area, like many, is blighted by signs etc not removed.
Posted anonymously at 17:38, Mon 23 December 2024
-
State changed to: In progress
Updated by Hampshire County Council at 08:33, Tue 24 December 2024
-
State changed to: Open
Updated by Hampshire County Council at 08:20, Tue 31 December 2024
-
Still open, via questionnaire, 23:22, Friday 17 January 2025
-
The low ironwork is still not fixed. A dangerous hazard to cyclists and da.aging to vehicles.
Posted anonymously at 23:25, Friday 17 January 2025
-
State changed to: In progress
Updated by Hampshire County Council at 08:42, Monday 20 January 2025
-
State changed to: Action scheduled
Updated by Hampshire County Council at 13:49, Thursday 13 February 2025
-
Recently low ironwork signs have reappeared. Is this an indication that the work is not going to be done. If there's an incident Highways will just say you've been warned.
Posted anonymously at 16:42, Wednesday 5 March 2025
-
State changed to: In progress
Updated by Hampshire County Council at 16:58, Wednesday 5 March 2025
-
What does 'in progress' mean. This phrase has been used numerous times since first reported in November with no action happening. A hazard has been created with little urgency to restore a safe environment.
Posted anonymously at 19:05, Wednesday 5 March 2025
-
State changed to: Action scheduled
Updated by Hampshire County Council at 08:39, Thursday 6 March 2025
-
Absolutely nothing is happening despite supposedly being scheduled for the 12/13 March. Also Highways map shows action scheduled for Hall Lane end but low ironworks are between The Link and Bracken Lane r'bout.
Posted anonymously at 13:17, Thursday 13 March 2025
-
State changed to: In progress
Updated by Hampshire County Council at 14:20, Thursday 13 March 2025
-
State changed to: Closed
Updated by Hampshire County Council at 12:53, Wednesday 19 March 2025
-
This job is not closed. We have been told numerous times the work is scheduled or in progress. I've also had an email from Highways saying it was scheduled to happen 12/13 March. Now another email seems to indicate it's put off again and is with the programming team.
Posted anonymously at 13:11, Wednesday 19 March 2025
-
State changed to: In progress
Updated by Hampshire County Council at 15:16, Wednesday 19 March 2025
-
State changed to: Closed
Updated by Hampshire County Council at 09:06, Wednesday 26 March 2025
-
Despite no action Highways deem this closed as they've passed the buck to the contractor. It is Highways responsibility until the job is done. What they're saying is we've closed the enquiry because we've passed it on. This is unacceptable.
Posted anonymously at 16:53, Friday 28 March 2025
-
State changed to: In progress
Updated by Hampshire County Council at 08:52, Monday 31 March 2025
-
State changed to: No further action
Updated by Hampshire County Council at 10:17, Thursday 3 April 2025
-
Is this a late April Fool? Hampshire have acknowledge the low ironworks and indeed returned and put signage up. Now they have the audacity to put no further action.
Posted anonymously at 11:18, Thursday 3 April 2025
-
State changed to: In progress
Updated by Hampshire County Council at 11:22, Thursday 3 April 2025
-
State changed to: Closed
Updated by Hampshire County Council at 12:07, Thursday 3 April 2025
-
This is NOT closed until the job is done
Posted anonymously at 13:05, Thursday 3 April 2025
-
State changed to: In progress
Updated by Hampshire County Council at 14:16, Thursday 3 April 2025
-
State changed to: Action scheduled
Updated by Hampshire County Council at 14:24, Thursday 3 April 2025