Double white lines fading
Reported via desktop in the Road Marking category anonymously at 11:58, Mon 21 October 2024 using FixMyStreet Pro
Sent to Bromley Council less than a minute later. FixMyStreet ref: 6640340.
The double white lines on the centre of Beckenham Lane are becoming seriously faded due to wear. The lines go all the way down to Shortlands from the Magistrates Court. A dangerous road to start with hence the double white lines in the centre. Drivers starting to wander towards oncoming traffic, especially now winter evenings are drawing in.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 11:59, Mon 21 October 2024
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 10:43, Tue 22 October 2024
-
These works are currently outstanding with our Minor Works contractor and should be completed soon.
Posted by Bromley Council
at 10:39, Fri 6 December 2024
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 17:05, Thursday 23 January 2025
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 11:50, Friday 31 January 2025
-
These works are currently outstanding with our Minor Works contractor and should be completed soon.
Posted by Bromley Council
at 17:21, Tuesday 11 February 2025
-
These works are currently outstanding with our Minor Works contractor and should be completed soon.
Posted by Bromley Council
at 14:21, Monday 24 March 2025
-
We are sorry that this work has not yet been completed. We are working with our minor works contractor in an effort to resolve this issue.
Posted by Bromley Council
at 14:35, Friday 28 March 2025
-
We are sorry that this work has not yet been completed. We are working with our minor works contractor in an effort to resolve this issue.
Posted by Bromley Council
at 13:41, Wednesday 30 April 2025
-
We are sorry that this work has not yet been completed. We are working with our minor works contractor in an effort to resolve this issue.
Posted by Bromley Council
at 13:53, Thursday 8 May 2025
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 16:00, Wednesday 14 May 2025
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 15:08, Thursday 5 June 2025
Only the original reporter may leave updates. If you made the original report please log in to leave an update.