Drainage cuts blocked

Reported via mobile in the Blocked Ditch category anonymously at 11:43, Mon 7 October 2024

Sent to West Northamptonshire Council less than a minute later. FixMyStreet ref: 6560792.

The road side drainage cuts haven't been cleared for years and no road runoff water can go down them now into the ditch. These need digging out and clearing to stop the flooding at the bottom of the road.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 11:43, Mon 7 October 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38 days.

    Posted by West Northamptonshire Council at 08:41, Tue 15 October 2024

  • Still open, via questionnaire, 13:25, Mon 4 November 2024

  • Still open, via questionnaire, 14:51, Mon 2 December 2024

  • Still open, via questionnaire, 16:45, Mon 30 December 2024

  • Still open, via questionnaire, 18:29, Mon 27 January 2025

  • Still open, via questionnaire, 18:42, Mon 24 February 2025

  • The 6 months deadline has passed and no work has been done. Road has repeatedly flooded due to this issue. Very disappointing given the ever rising council tax we pay.

    Posted anonymously at 19:10, Mon 24 March 2025
    Still open, via questionnaire

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38 days.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 13:57, Mon 31 March 2025

  • Still open, via questionnaire, 20:17, Mon 21 April 2025

  • Still open, via questionnaire, 20:32, Mon 19 May 2025

  • Still open, via questionnaire, 21:17, Mon 16 June 2025

  • Still open, via questionnaire, 21:33, Mon 14 July 2025

  • Waste of my time. Scheduled repair within 26 weeks. Its now 11 months and counting.

    Posted anonymously at 22:14, Mon 11 August 2025
    Still open, via questionnaire

  • Investigation: Not Started (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 12:01, Tue 12 August 2025

  • Still open, via questionnaire, 08:24, Tue 9 September 2025

  • Still open, via questionnaire, 09:58, Tue 7 October 2025

  • Still open, via questionnaire, 10:04, Tue 4 November 2025

  • Still open, via questionnaire, 10:43, Tue 2 December 2025

  • 1 year and 4 months since reporting this problem and still nothing. What is the point of this service?

    Posted anonymously at 11:09, Tue 30 December 2025
    Still open, via questionnaire

  • Investigation: Ongoing (Defect Found), Defect Repair: Scheduled - Thank you for your enquiry. Please accept our apologies that this has not yet been attended to. Recent weather events have required us to reprioritise other essential works, which has unfortunately caused a knock-on delay to this activity. We are now rescheduling these works as a priority and will update the report with revised timescales within the next 7 days.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 11:03, Wednesday 14 January 2026

  • Still open, via questionnaire, 12:05, Tuesday 27 January 2026

  • Investigation: Ongoing (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 12:58, Tuesday 3 February 2026

  • Investigation: Ongoing (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 13:46, Tuesday 3 February 2026

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed - We have attended the location and works have been completed. Your enquiry will now be closed. If for any reason you believe we have not attended the correct defect, please inform us by raising a new enquiry.

    Posted by West Northamptonshire Council at 12:15, Thursday 5 March 2026

This report is now closed to updates from the public. You can make a new report in the same location.