Big pothole

Reported via desktop in the Pothole category anonymously at 16:00, Wed 2 October 2024

Sent to Hampshire County Council less than a minute later. FixMyStreet ref: 6543570.

Big pot home right on junction (thanks for fixing other potholes this year)

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • State changed to: In progress

    Updated by Hampshire County Council at 16:33, Wed 2 October 2024

  • State changed to: Action scheduled

    Updated by Hampshire County Council at 11:12, Thu 3 October 2024

  • State changed to: In progress

    Updated by Hampshire County Council at 08:55, Tue 29 October 2024

  • State changed to: Action scheduled

    Updated by Hampshire County Council at 15:04, Tue 29 October 2024

  • It was showing *”Action Scheduled” on 3rd October. So we followed up October 26 as we thought action would have been taken to get the work done by now. And we all wanted Council to know it is much worse than October 3rd - so that might mean the “triage” they mentioned in one of their emails brings the work forward. “On Saturday 26 October it was *”In Progress”. And now an email *“ a job has been raised and is with the contractor to schedule the works”. We have asked the Council, Any possibility of an estimated date of when the pot hole will be filled please?

    And would it be possible to give us the standard estimated time for each of the 3 status updates I have marked with a * above please?

    Posted anonymously at 17:01, Wed 30 October 2024
    Still open, via questionnaire

  • State changed to: In progress

    Updated by Hampshire County Council at 08:38, Thu 31 October 2024

  • State changed to: Action scheduled

    Updated by Hampshire County Council at 09:07, Mon 18 November 2024

  • Still open, via questionnaire, 18:08, Wed 27 November 2024

  • It was showing *”Action Scheduled” on 3rd October. So we followed up October 26 as we thought action would have been taken to get the work done by now. And we all wanted Council to know it is much worse than October 3rd - so that might mean the “triage” they mentioned in one of their emails brings the work forward. “On Saturday 26 October it was *”In Progress”. And now an email *“ a job has been raised and is with the contractor to schedule the works”. We have asked the Council, Any possibility of an estimated date of when the pot hole will be filled please?

    And would it be possible to give us the standard estimated time for each of the 3 “status updates “ amounting to nothing I have marked with a * above please?

    Posted anonymously at 18:10, Wed 27 November 2024

  • State changed to: In progress

    Updated by Hampshire County Council at 08:51, Thu 28 November 2024

  • State changed to: Action scheduled

    Updated by Hampshire County Council at 14:49, Fri 29 November 2024

  • State changed to: Fixed

    Updated by Hampshire County Council at 11:04, Tue 3 December 2024

Only the original reporter may leave updates. If you made the original report please log in to leave an update.