Unfinished reinstatement

Reported via mobile in the Road Defect category anonymously at 08:38, Sat 27 April 2024 using FixMyStreet Pro

Sent to Bromley Council less than a minute later. FixMyStreet ref: 5904645.

Following works to the pedestrian island, tarmac has not been reinstated around it.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 08:40, Sat 27 April 2024

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 11:40, Mon 29 April 2024

  • Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.

    Posted by Bromley Council at 08:45, Wed 5 June 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 12:04, Thu 18 July 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 09:34, Wed 14 August 2024

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 10:57, Wed 11 September 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 11:05, Fri 20 September 2024

  • Further works are necessary to resolve the issue and have been scheduled for action.

    State changed to: In progress

    Posted by Bromley Council at 09:02, Thu 26 September 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 13:14, Mon 30 September 2024

This report is now closed to updates from the public. You can make a new report in the same location.