Deteriorating ‘trench’ in centre of road outside ‘Thorndale’….

Reported via desktop in the Road Defect category anonymously at 09:20, Mon 8 April 2024

Sent to Bromley Council less than a minute later. FixMyStreet ref: 5821906.

….now exposing underlying base substrate stones….

See attached 8am Monday 8 April photos….

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 09:21, Mon 8 April 2024

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 11:49, Wed 10 April 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 07:42, Fri 24 May 2024

  • When will this deteriorating ‘trench’ be fixed?

    Why is it taking so long to do these basic maintenance repairs?

    Why, given your comments reported in the Newsshopper newspaper (page 5 May 22nd edition) are you, Bromley Council seemingly unable (or is it unwilling?) to ‘practice what you “preach”….’

    Quote:

    “….the reality is that we have a methodical and logical process for repairs….we have reduced the number of potholes very considerably….”

    Is quite frankly ‘laughable’….there are tens in not hundreds of long reported unfixed holes and trenches in Chislehurst alone……walk along the busy A222 from the Frognal roundabout west…..and count them!

    Photos attached taken 8am Friday 24 May.

    Please advise WHEN this ‘trench’ will be fixed.

    Posted anonymously at 10:15, Fri 24 May 2024

  • Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.

    Posted by Bromley Council at 09:22, Wed 5 June 2024

  • Photos attached taken 8am Wednesday 12 June…

    How many potholes are filled in Chislehurst Ward per week one wonders……does Bromley Council have the figures?

    Posted anonymously at 12:12, Wed 12 June 2024

  • Thank you for your update.

    Thank you for using Fix My Street.

    Posted by Bromley Council at 10:42, Wed 26 June 2024

  • See attached photos……following Riney’s repair at c.9am on Friday 28 June. Good ‘news’…..

    But:

    - Note the tarmac section is considerably smaller than the white marked out area.

    - The ‘rough’ area on the western (downhill) side

    - The lack of bitumised seal around the 4 sides to minimise water ingress at the edges….

    - The other, marked up, defects in Lubbock Road were not done at the same time….why not?

    Is this the best managed, ‘commonsense’, cost effective approach by Bromley Council to ensure optimal value for money from limited public funds? One wonders…..

    Posted anonymously at 05:41, Mon 1 July 2024

  • Thank you for your update.

    Thank you for using Fix My Street

    Posted by Bromley Council at 19:40, Tue 2 July 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 12:32, Mon 15 July 2024