Long and deep potholes in elmstead lane

Reported via desktop in the Road Defect category anonymously at 12:09, Saturday 30 March 2024

Sent to Bromley Council less than a minute later. FixMyStreet ref: 5784739.

SOME AREAS RE-SURFACED YET NUMEOUS DEEP AND LONG POTHLES REMAIN THOUGHTOUT LENGHT OF ROAD. DANGEROUS TO MOTORCYCLISTS, CYCLISTS AND MOTORISTS. not attended to for a considerable time

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 12:10, Saturday 30 March 2024

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 15:05, Tuesday 2 April 2024

  • Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.

    Posted by Bromley Council at 12:53, Thursday 18 April 2024

  • Still open, via questionnaire, 12:47, Saturday 27 April 2024

  • Holes growing!

    Posted anonymously at 11:37, Sunday 26 May 2024
    Still open, via questionnaire

  • Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.

    Posted by Bromley Council at 17:01, Monday 3 June 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 09:00, Thursday 6 June 2024