You can move around with your keyboard
plus
minus
left
right
Drop pin on the map to start a new report
space
Press space again to adjust the location
space
Start new report here Reposition report here
Back to all reports

Deep rut spanning the whole width of the road.

Reported via desktop in the Potholes / Highway Condition category anonymously at 20:54, Fri 22 March 2024 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5755084.

The location of this is on the main Boughton Green Road, almost on the junction with University Close. Dry dangerous for cyclists, motorbikes as well as cars.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 20:55, Fri 22 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and we hope for the work to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 10:28, Mon 25 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 12:23, Tue 11 June 2024

  • Still not resolved. rut getting worse. Surely this should be placed on the utility company who backfilled to resolve?

    Posted anonymously at 14:15, Thu 29 August 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on FMS-5755084-1 and add updates. The expected completion date for these works will be 21/09/2024.

    Posted by Northamptonshire Highways at 07:22, Mon 2 September 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 11:47, Thu 5 September 2024

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 14:31, Thu 5 September 2024

This report is now closed to updates from the public. You can make a new report in the same location.