Patching upon patching
Reported via desktop in the Potholes / Highway Condition category by Cllr Peter Matten at 17:01, Wednesday 20 March 2024
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5744309.
This is a breaking area on the approach to a roundabout. A particularly dangerous area as drivers are looking for vehicles coming around the roundabout rather than looking out for pot holes, resulting in late decision making / breaking / avoidance moves. This stretch of road was repaired within the last 12 months. And now it needs doing again (as per my photo's). Can we please do a large enough repair that it won't need re-visiting again this year? Many thanks.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 17:01, Wednesday 20 March 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and we hope for the work to be carried out within the next 26 weeks. You will receive further information when this job is completed.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by Northamptonshire Highways at 10:59, Monday 25 March 2024
-
Good evening, An update for you. Hole is now 3 inches deep.
Posted by Cllr Peter Matten at 21:27, Thursday 11 April 2024
-
The biggest hole is getting worse.
Posted by Cllr Peter Matten at 11:48, Thursday 18 April 2024
Still open, via questionnaire -
The. Pot hole on the inside of the road at the junction of the road about is getting bigger day by day.
Posted anonymously at 09:08, Thursday 25 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and we hope for the work to be carried out within the next 26 weeks. You will receive further information when this job is completed.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by Northamptonshire Highways at 15:13, Wednesday 26 June 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 11:23, Thursday 25 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by Northamptonshire Highways at 07:59, Friday 2 August 2024
Provide an update
Your information will only be used in accordance with our privacy policy