Failed road crossing

Reported via mobile in the Potholes / Highway Condition category anonymously at 18:28, Monday 4 March 2024

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5667732.

Tarmac has failed due to a reinstated road crossing close to the church gates on the road, more damage to tarmac surface along this stretch of road, near constant water flow down side from the top of the hill crosses the road with road fall and streams down other side, water possibly from under ground stream over flowing, tarmac surface appears to heaved up due to expansion in places

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 18:28, Monday 4 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have instructed works to be undertaken within the next 28 days to rectify these issues. You will receive updates once completed.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 10:10, Monday 11 March 2024

  • Still the same all along here

    Posted anonymously at 18:36, Monday 1 April 2024
    Still open, via questionnaire

  • Investigation: Not Started (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 07:10, Friday 5 April 2024

  • Investigation: Not Started (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 11:09, Monday 8 April 2024

  • Investigation: Not Started (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 11:31, Monday 8 April 2024

  • Investigation: Completed (Work Completed), Defect Repair: Work Completed - An inspector has been sent to the area and the defect was resolved on April 8th 2024

    Posted by Northamptonshire Highways at 15:49, Monday 8 April 2024

This report is now closed to updates from the public. You can make a new report in the same location.