Uneven Pathway near the Post Office on Sheep Street

Reported via desktop in the Slabs - Uneven / Damaged / Cracked category anonymously at 11:07, Monday 4 March 2024 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5664757.

A lady has fallen on the pathway on Sheep Street, coming from the Market Place before reaching the Post Office. There is a jewellers near by. She fell on Saturday and has injured both knees and her hand, other members of the public had to help her up. She has not been able to go into work today. She would like an Officer to assess the block paving in that area to prevent further accidents.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 11:08, Monday 4 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Highways are sorry to hear about the lady's fall. The area has been inspected and we hope for the work to be carried out within the next 28 days. You will receive further information when this job is completed. We have also referred other defects close to your concern to the relevant teams at Anglian Waters and BT, who will investigate this further. Please contact them directly for further information.

    Posted by Northamptonshire Highways at 12:57, Monday 11 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 12:36, Thursday 14 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 07:53, Saturday 16 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 08:17, Saturday 16 March 2024

This report is now closed to updates from the public. You can make a new report in the same location.