Reported via desktop in the Potholes / Highway Condition category anonymously at 13:47, Monday 26 February 2024 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5633274.

Several potholes need attention/repair Stonelea Road

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 13:48, Monday 26 February 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have inspected this carriageway and have arranged for remedial works to be undertaken within 26 weeks. You will receive a further update once works are complete.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 19:45, Monday 4 March 2024

  • Stonelea Road Sywell - your team came to site 28th or 29th March - did two potholes - left rest (at leastr five plus the junction with main road) which were all still marked - why send whole work team and do half job? Bad planning even if on two work tickets?

    Posted anonymously at 10:38, Sunday 31 March 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Some defects were classified as a higher priority and had to be completed sooner for safety reasons. We have to prioritise the whole county on safety so sometimes we cannot complete all defects at once. We have to ensure our limited resource is disrupted on the safety concerns first and foremost. We hope this has helped to explain things and further defects will be completed on or before 2 September 2024.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 13:09, Monday 8 April 2024