Fixed
Pothole next to drain that is getting worse
Reported via mobile in the Blocked/Damaged category anonymously at 14:22, Sat 24 February 2024
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5624980.
Pothole since winter hole next to drain is getting worse and drain cover keeps making noise every time a car goes over. The. Noise is handy if the wife is coming home but usually it's a car. Lol
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 14:22, Sat 24 February 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and depending on weather conditions we hope for the work to be carried out within the next 28 days. You will receive further information when this job is completed.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 09:55, Thu 29 February 2024
-
Still open, via questionnaire, 14:57, Sat 23 March 2024
-
Still open, via questionnaire, 15:36, Sat 20 April 2024
-
Other pot holes in chancery Lane have been fixed while others in same road very close by have not. Why not fix all potholes in same road?
Posted anonymously at 18:01, Sat 18 May 2024
Still open, via questionnaire -
Investigation: Ongoing (Duplicate), Defect Repair: Not Started - An inspector has been sent to the area and we hope to have this resolved by September 3rd 2024
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 21:53, Fri 24 May 2024
-
Still open, via questionnaire, 06:05, Sun 16 June 2024
-
Investigation: Ongoing (Duplicate), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:50, Mon 17 June 2024
-
Investigation: Ongoing (Duplicate), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 16:28, Wed 19 June 2024
-
Investigation: Ongoing (Duplicate), Defect Repair: Work Completed
State changed to: Fixed
Posted by Northamptonshire Highways at 16:44, Wed 19 June 2024
-
Great job
Posted anonymously at 06:38, Sun 14 July 2024
-
Investigation: Completed (Work Completed), Defect Repair: Work Completed - Thank you for your further feedback following completion of these repair works.
Posted by Northamptonshire Highways at 08:31, Mon 19 August 2024
This report is now closed to updates from the public. You can make a new report in the same location.