Fixed
Two large potholes on bridge
Reported via desktop in the Potholes / Highway Condition category anonymously at 21:57, Mon 19 February 2024
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5602076.
The bridge over the A45, southbound (towards rushden) two large pot holes have grown at the joint for the bridge with the rest of the road, one of them is very deep
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 21:57, Mon 19 February 2024
-
Investigation: Completed (Work Completed) - An inspector has been sent to the area and the defect was resolved on February 21st 2024
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysState changed to: Fixed
Posted by Northamptonshire Highways at 13:00, Mon 26 February 2024
-
They fixed one, left the other, well done, great work. is the contractor the same person that tried to steal all the dogs in a 101 Dalmatians?
State changed to: Open
Posted anonymously at 18:49, Wed 20 March 2024
Still open, via questionnaire -
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 18:50, Wed 20 March 2024
-
Investigation: Completed (Work Completed), Defect Repair: Not Started - The area has been inspected and we hope for the work to be carried out within the next 26 weeks, though we hope to complete the works as soon as possible. You will receive further information when this job is completed.
Posted by Northamptonshire Highways at 14:38, Wed 27 March 2024
-
Investigation: Completed (Work Completed), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 09:58, Wed 10 April 2024
-
Investigation: Completed (Work Completed), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 14:16, Mon 15 April 2024
-
Investigation: Completed (Work Completed), Defect Repair: Work Completed
State changed to: Fixed
Posted by Northamptonshire Highways at 10:18, Wed 18 September 2024
This report is now closed to updates from the public. You can make a new report in the same location.