Fixed
2 potholes in North St
Reported via desktop in the Potholes / Highway Condition category anonymously at 18:07, Monday 12 February 2024 using FixMyStreet Pro
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5567932.
Outside 26 & 39 North St potholes but all of North St is breaking down causing problems driving in the street the deterioration has been going on for many years
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 18:07, Monday 12 February 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and depending on weather conditions we hope for the work to be carried out within the next 26 weeks. You will receive further information when this job is completed.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 14:23, Monday 19 February 2024
-
I reported this pothole in February and it’s still not been repaired. It’s now bigger and deeper and there is cracking developing across the road.The stones from the breakdown of the tarmac are being thrown out by vehicles hitting the hole. My car could be damaged as this is outside my property where I park.
Posted anonymously at 15:17, Monday 10 June 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Works to be completed by 19th August You will receive further information when this job is completed.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 09:31, Thursday 27 June 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 14:02, Thursday 1 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 12:53, Monday 5 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by Northamptonshire Highways at 09:16, Thursday 8 August 2024