Hold outside my house was filled with concrete and not tarmaced

Reported via mobile in the Pavement Defect category anonymously at 10:23, Mon 12 February 2024 using FixMyStreet Pro

Sent to Bromley Council less than a minute later. FixMyStreet ref: 5564772.

Please come and re-tarmac outside of my property, 4 Fenton Close. A large hole was resurfaced, and simply filled with concrete. No tarmac applied. It is an eyesore and also starting to crack, which will become unsafe again.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 10:23, Mon 12 February 2024

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 16:14, Mon 12 February 2024

  • Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.

    Posted by Bromley Council at 11:02, Tue 19 March 2024

  • Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.

    Posted by Bromley Council at 12:45, Thu 18 April 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 16:31, Tue 4 June 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 11:57, Thu 18 July 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time

    Posted by Bromley Council at 09:06, Wed 14 August 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time

    Posted by Bromley Council at 10:53, Tue 24 September 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 19:40, Wed 2 October 2024