Investigating
5-6 deep potholes
Reported via mobile in the Potholes / Highway Condition category anonymously at 14:01, Fri 9 February 2024 using FixMyStreet Pro
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5554322.
There is 5/6 deep pot holes that are in need of repair - risk of damage to cars and to many to dodge
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 14:01, Fri 9 February 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and depending on weather conditions we hope for the work to be carried out within the next 26 weeks. You will receive further information when this job is completed.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by Northamptonshire Highways at 11:15, Thu 15 February 2024
-
Constant school traffic has made these pothole significantly worse and if when hit due to the large amount damage is now occuring.
Residents should not have to suffer due to the schools lack of parking and the abuse of the road by far to many cars and risk damaging their own vehicles and a 26 week wait is not acceptable. Now over 10 potholes.
Pictures uploaded.
Posted anonymously at 19:20, Mon 1 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We have inspected the area and can confirm this will be rectified within 26 weeks, we hope to be conducting the repairs by August 15th 2024
Posted by Northamptonshire Highways at 13:07, Thu 4 April 2024
-
So until August 2024 we have to hope that no elderly neighbour (who are 90 years of age and it is the road to their home) or church goer or school kids injure themselves in the mean time.
Posted anonymously at 14:09, Thu 4 April 2024
-
Investigation: Not Started (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 07:40, Wed 10 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled - We have inspected the area and can confirm this will be rectified within 26 weeks, however, we hope to be conducting the repairs by April 22nd 2024
Posted by Northamptonshire Highways at 09:52, Thu 11 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 10:23, Mon 22 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days.
Posted by Northamptonshire Highways at 14:08, Mon 22 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Rejected
State changed to: Investigating
Posted by Northamptonshire Highways at 09:40, Tue 23 April 2024
Provide an update