Multiple potholes and sunken drains
Reported via mobile in the Road Defect category anonymously at 08:32, Wed 31 January 2024
Sent to Bromley Council less than a minute later. FixMyStreet ref: 5513452.
There are multiple potholes and road defects on Elmstead lane. Also sunken drains
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 08:33, Wed 31 January 2024
-
In need of attention please
Posted anonymously at 07:58, Thu 1 February 2024
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 12:47, Thu 1 February 2024
-
Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.
Posted by Bromley Council
at 12:49, Wed 13 March 2024
-
First reported 42 days ago
Posted anonymously at 21:10, Wed 13 March 2024
-
The road here is getting more sunken each day and looks like a sinc hole could easily appear at some stage
Posted anonymously at 15:39, Thu 21 March 2024
-
First reported fifty days ago
Posted anonymously at 20:59, Thu 21 March 2024
-
For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake these works.
Posted by Bromley Council
at 10:31, Wed 1 May 2024
-
First reported 91 days ago
Posted anonymously at 16:31, Wed 1 May 2024
-
For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake these works.
Posted by Bromley Council
at 15:31, Thu 30 May 2024
-
First reported 120 days ago
Posted anonymously at 16:17, Thu 30 May 2024
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 09:57, Tue 4 June 2024
-
2024 Thank you for your report regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.
Posted by Bromley Council
at 10:19, Thu 4 July 2024
-
First reported 155 days ago. Very disappointing indeed.
Posted anonymously at 18:40, Thu 4 July 2024
-
Thank you for your update, Further investigation is required to resolve this matter. We apologise for the delay.
Posted by Bromley Council
at 12:28, Thu 29 August 2024
-
First reported 211 days ago
Posted anonymously at 17:56, Thu 29 August 2024
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 15:50, Mon 9 September 2024
-
222 days to fix.
Posted anonymously at 16:40, Mon 9 September 2024
This report is now closed to updates from the public. You can make a new report in the same location.