Large pothole at the junction of Greenacre Drive and Bedford Road. Can't turn out without going down it.
Reported via desktop in the Potholes / Highway Condition category anonymously at 12:45, Monday 22 January 2024
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5475173.
There is a large pothole which has been very badly repaired and has reappeared
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 12:46, Monday 22 January 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that the carriageway defects meet the investigatory level for repairs and work has been scheduled to resolve them. This should be completed within a 28 day time frame and please be assured that you will receive an update once repairs are concluded.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 10:04, Tuesday 30 January 2024
-
Still open, via questionnaire, 13:31, Monday 19 February 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 09:21, Wednesday 21 February 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 11:40, Thursday 22 February 2024
-
Investigation: Completed (Defect Found), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days.
Posted by Northamptonshire Highways at 12:02, Thursday 22 February 2024
-
They came and put loose chippings in the holes which have come ut and the holes have returned
Posted anonymously at 14:42, Monday 18 March 2024
Still open, via questionnaire -
Investigation: Not Started (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:20, Thursday 21 March 2024
-
Investigation: Not Started (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 11:54, Friday 22 March 2024
-
Investigation: Not Started (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by Northamptonshire Highways at 12:40, Friday 22 March 2024
-
Investigation: Completed (Work Completed), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days. - An inspector has been sent to the area and the defect was resolved on March 22nd 2024. For any new concerns you may have about the roads and pathways in Northamptonshire please report them as a separate report at the following link: https://fixmystreet.northamptonshire.gov.uk/
State changed to: In progress
Posted by Northamptonshire Highways at 16:18, Monday 25 March 2024
-
Still open, via questionnaire, 15:14, Monday 15 April 2024
-
Questionnaire filled in by problem reporter; State changed to: Fixed, 16:10, Monday 13 May 2024