Blocked drain causing flooding

Reported via desktop in the Blocked - flooding road/path category anonymously at 11:19, Fri 22 December 2023 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5348439.

Drain immediately outside the property (to the south) is blocked and the road is currently flooded. There is an ongoing issue here which means it keeps getting blocked regularly. Phoned through to the HUB and emailed Highways to discuss ongoing problem. Resident believes a pipe has collapsed.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 11:19, Fri 22 December 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 16:39, Tue 2 January 2024

  • Still an issue. 😠

    Posted anonymously at 13:57, Sat 3 February 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 13:57, Sat 3 February 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 11:35, Tue 6 February 2024

  • After heavy rain continuous flooding into the swing park containing tissue which suggests sewage, potentially posing a health risk as a children’s play area. Requires immediate attention.

    Posted anonymously at 14:49, Sun 18 February 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 14:49, Sun 18 February 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 15:32, Tue 20 February 2024

  • Raw sewage in the play park as a result of the blocked drain causing flooding in the road and pavement. This needs escalating and cannot be left for 26 weeks. This is a problem that has been going on for years now and is the worst it’s been. This is a serious health risk given the location of where this is draining.

    Posted anonymously at 20:21, Tue 20 February 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 20:21, Tue 20 February 2024

  • Investigation: Completed (Reported to a third party), Defect Repair: Not Started - As this is not a Highways matter, we have referred it to the relevant team at Anglian Waters, who will investigate this further. Please contact them directly for further information. The reference number for this job is 25270948.

    Posted by Northamptonshire Highways at 12:35, Thu 22 February 2024

  • Spoke to Anglian Water today quoting above reference and they stated that their investigations were carried out yesterday and that there was no pollution found in the water from their samples taken. They advised their sewerage drains were clear and that there was a block highways gully which is your responsibility to fix. This problem has been ongoing since last year and still remains an issue. please update asap on next steps.

    Posted by Syresham Parish Council at 13:50, Thu 22 February 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 13:50, Thu 22 February 2024

  • This has been going on much longer than a year. We repeatedly report this problem on average at least once a month and has been an issue since the original road was reprofiled in 2017. This has been reported and asked to be escalated a number of times and no action has been taken aside from unblocking the defected drain. Please could this be repaired to prevent this happening. It’s clearly costly someone being called out every time to unblock this.

    Posted anonymously at 14:12, Thu 22 February 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have raised a works order to repair the gully within the next 26 weeks.

    Posted by Northamptonshire Highways at 16:14, Mon 26 February 2024

  • Can it be confirmed the repair will be completed no later than 26 weeks from when the original inspection took place on January 2nd? The most recent inspection is only confirming the existing issue.

    Posted anonymously at 20:13, Mon 26 February 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 20:13, Mon 26 February 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - To be clear, we will be carrying out investigation works here to ascertain the internal drainage problems. This will be completed on or before 2nd July 2024. Once we have the results we will schedule a repair. Drainage investigations can take some time. We appreciate your patience.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 16:23, Wed 28 February 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 07:52, Fri 14 June 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:51, Mon 17 June 2024

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 09:49, Tue 16 July 2024

This report is now closed to updates from the public. You can make a new report in the same location.