Verge has collapsed in Grays Rd, Safety fencing has been pit around the hole. The fencing is narrowing the poad.

Reported via mobile in the Road Defect category anonymously at 12:35, Thu 7 December 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 5292334.

The fencing has been in place for a couple of weeks

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 12:35, Thu 7 December 2023

  • We are continuing to investigate and working to resolve this report

    Posted by Bromley Council at 11:21, Thu 14 December 2023

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 20:50, Thu 28 December 2023

  • Still open, via questionnaire, 13:41, Thursday 4 January 2024

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 15:29, Saturday 20 January 2024

  • Resident has phoned to state road is still narrowing and is becoming more dangerous

    Posted by Bromley Council at 11:02, Thursday 15 February 2024

  • Why is this repair taking so long? Reported in early DECEMBER! Every time it rains it can only be getting worse. Is someone waiting to see how long it is before a car actually disappears into it?

    Posted anonymously at 18:31, Tuesday 5 March 2024

  • Works have been delayed following the identification of a gas main in close vicinity to the void you have reported. Our contractor is working with SGN to resolve this issue. The site has even inspected this morning and guarding is being maintained for public safety. We appreciate your continued patience.

    Posted by Bromley Council at 11:37, Tuesday 19 March 2024

  • The contractors are still in negotiations with the gas board concerning the void repairs in Grays Road and will maintain the site safety until works to repair site are agreed.

    Posted by Bromley Council at 11:50, Tuesday 16 April 2024

  • The contractors are still in negotiations with the gas board concerning the void repairs in Grays Road and will maintain the site safety until works to repair site are agreed.

    Posted by Bromley Council at 11:50, Tuesday 16 April 2024

  • The void repair job has been scheduled for completion on Tue 21/5, under road closure.

    Posted by Bromley Council at 12:54, Monday 20 May 2024

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 08:26, Thursday 23 May 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 06:34, Friday 24 May 2024

  • Our contractor has been notified to take the appropriate action.

    State changed to: In progress

    Posted by Bromley Council at 10:43, Tuesday 11 June 2024