Temporary traffic lights

Reported via desktop in the Roads and Carriageways category anonymously at 18:32, Mon 27 November 2023

Sent to Oxfordshire County Council 1 minute later. FixMyStreet ref: 5258626.

Temporary traffic lights have appeared with no advance notice just to the East of Marcham on the A415.

No sign of any work taking place; there were certainly no workers on sight.

I see from One Network they are to do with Open Reach. Why was no notice of the works given?

As they are going to be here for 2 weeks they must be manned at peak times. The queue from Abingdon was back beyond the Marcham interchange at 4.45 pm this evening.

Finally arriving at the lights only 4 cars at a time we're being let through. Woefully inadequate.

Council ref: ENQ23982043

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your enquiry. This issue has been passed onto the relevant team for investigation.

    State changed to: Investigating

    Posted by Oxfordshire County Council at 18:33, Mon 27 November 2023

  • Sunday 3d December the temporary traffic lights are not working on the A415 at 4.15pm . Going into Abingdon the lights are off but they seem to be working from abingdon to Marcham. Therefore the traffic coming from Marcham does not know when to go. Urgent as a main road. L Mott Anson Close

    Posted anonymously at 17:42, Sun 3 December 2023

  • At 10:20pm this problem remains and presents a real danger at night and in wet conditions.

    Posted anonymously at 22:21, Sun 3 December 2023

  • Monday evening 5PM (04.12.23) work had clearly completed and yet traffic lights remained causing the usual avoidable delays (if only the lights had been manned - or in this case removed)!

    Lights remained in situ at 7AM this morning (05.12.23) again causing delays and again should have been removed Monday PM

    Woeful contracting

    Posted anonymously at 15:39, Tue 5 December 2023

  • Thank you for your enquiry this has been forwarded to our Network Management team to investigate.

    State changed to: Investigation complete

    Posted by Oxfordshire County Council at 11:41, Friday 9 February 2024

This report is now closed to updates from the public. You can make a new report in the same location.