Massive long pothole around the whole roundabout!

Reported via mobile in the Potholes / Highway Condition category anonymously at 15:34, Thu 9 November 2023 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5193558.

Pothole has gradually increased around the middle of the whole roundabout and leading off towards the Morris Home site which again the road is BLOODY AWFUL and was meant to be temporary surface and this was over a year ago

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 15:34, Thu 9 November 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Having inspected the above-mentioned road we can confirm we have scheduled maintenance in the area within the next 26 weeks, as per our priority levels. But we hope to complete it as soon as possible. You will receive further updates once it has been completed.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 14:16, Fri 10 November 2023

  • This nearly had me off my motorbike in the dark last night - this one is deadly

    Posted anonymously at 09:55, Sun 24 December 2023

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 09:55, Sun 24 December 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Having inspected the above-mentioned road we can confirm we have scheduled maintenance in the area within the next 26 weeks, as per our priority levels. But we hope to complete it as soon as possible. You will receive further updates once it has been completed.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 16:41, Tue 2 January 2024

  • The potholes on the roundabout are getting worse and need fixing ASAP before damage occurs to vehicles. I have been in contact with Tilia homes to report this as this all happened when they dug up the roundabout but they don't seem to wat to respond to this or confirm if they will be fixing this. The road surface along the top of Wooldale road is also awful but again Tilia homes don't seem to want to fix this after digging that up aswell.

    Posted anonymously at 12:57, Mon 19 February 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 12:57, Mon 19 February 2024

  • Investigation: Ongoing (Duplicate), Defect Repair: Not Started - An inspector has been sent to the area and depending on weather conditions we hope to have this resolved by August 21st 2024

    Posted by Northamptonshire Highways at 12:50, Thu 22 February 2024

  • Investigation: Ongoing (Duplicate), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 08:49, Tue 16 April 2024

  • Investigation: Ongoing (Duplicate), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 15:25, Fri 26 April 2024

  • Investigation: Ongoing (Duplicate), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 16:16, Fri 26 April 2024

  • Investigation: Completed (Work Completed), Defect Repair: Work Completed - An inspector has been sent to the area and the defect was resolved on April 26th 2024

    Posted by Northamptonshire Highways at 11:31, Fri 3 May 2024