Large potholes in the road

Reported via desktop in the Potholes / Highway Condition category anonymously at 14:07, Thu 2 November 2023 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5166946.

A large number of deep potholes from the junction of Morland Road/to the very bottom of Constable Road for over a year now (Cul de Sac) These large deep potholes have been ignored the last couple of times the other section of Constable Road was repaired. It is now very difficult to drive to the bottom of the road without the chance of damaging the car.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 14:07, Thu 2 November 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that the carriageway defects meet the investigatory level for repairs and work has been scheduled to resolve them. This should be completed within a 6 month time frame and please be assured that you will receive an update once repairs are concluded.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 13:59, Mon 6 November 2023

  • Like a war zone lower end of Constable Rd towards cul de sac any damage to vehicles will be forwarded to North Northamptonshire

    Posted anonymously at 13:29, Thursday 4 January 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 13:29, Thursday 4 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that work will be completed here on/by 7th February 2024.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 14:03, Thursday 11 January 2024

  • Ref No. 5166946

    I did notice the white markings around some of the worst potholes but there are many more that seem to have been overlooked with no markings. Why does this happen ? and will they be left.The road is a disgrace and has ignored for over two years.

    Posted anonymously at 16:27, Thursday 11 January 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 16:27, Thursday 11 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that many works are due to be completed here on/by 7th February 2024. However other works will follow within the next 6 months. Any defects that meet criteria will be repaired in this time frame.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 09:11, Thursday 18 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 07:47, Friday 14 June 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 08:28, Monday 17 June 2024

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 13:48, Wednesday 19 June 2024

This report is now closed to updates from the public. You can make a new report in the same location.