Reported via mobile in the Potholes / Highway Condition category by Grzegorz kuropatwa at 16:40, Thu 26 October 2023

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5141429.

Road has got multiple potholes all around. Repairs last not more than 3 months and new are showing up on a weekly basis. Road needs to be resurfaced asap.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 16:40, Thu 26 October 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Having inspected the above-mentioned road we can confirm we have scheduled maintenance in the area within the next 26 weeks, as per our priority levels. But we hope to complete it as soon as possible. You will receive further updates once it has been completed.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 12:15, Mon 30 October 2023

  • Thanks for the update. Please make sure it's done properly this time. I observed how it was done back in April and that was disgraceful. I'm happy to share more information if needed.

    Posted anonymously at 16:17, Thu 2 November 2023

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 16:17, Thu 2 November 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Having inspected the above-mentioned road we can confirm we have scheduled maintenance in the area within the next 26 weeks, as per our priority levels. But we hope to complete it as soon as possible. You will receive further updates once it has been completed.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 11:05, Tue 7 November 2023

  • Still open, via questionnaire, 20:17, Thu 23 November 2023

  • Still open, via questionnaire, 05:51, Fri 22 December 2023

  • Gets worse and worse. Can someone please come and fix that road properly??? Looks worse than roads in Ukraine now.

    Posted anonymously at 14:00, Sun 14 January 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 14:01, Sun 14 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We have inspected the area and can confirm this will be repaired within 26 weeks, depending on weather conditions, we hope to be carrying out the repairs by April 26th 2024

    Posted by Northamptonshire Highways at 09:27, Fri 19 January 2024

  • It’s 10th of April. When we can expect to see the road being repaired? Is the job scheduled or no? Thanks

    Posted by Grzegorz Kuropatwa at 10:31, Wed 10 April 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - An inspector has been sent to the area and we hope to have this resolved by April 26th 2024
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 14:16, Tue 16 April 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 10:54, Wed 24 April 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 08:24, Fri 26 April 2024

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 06:57, Mon 29 April 2024

This report is now closed to updates from the public. You can make a new report in the same location.