Poor Remedial Repair

Reported via desktop in the Pavement Defect category by Mike Pinchen at 13:05, Wed 25 October 2023 using FixMyStreet Pro

Sent to Bromley Council less than a minute later. FixMyStreet ref: 5136159.

Recent remedial repairs (following damage by HGVs during the new school build), are of a poor low-quality standard. Some of the replacement curb stones are a different size, some are cracked/chipped, and some have not been reset/replaced at all. There are gaps between the ‘new’ curbs and the road surface, which will allow water to ingress, which when frozen will expand and create further problems. The ‘tarmac’ coating on the path has already started to erode in some places at curb level. It seems that Edgebury estate is treated as some sort of appendage, and that ‘we’ will put up with shoddy repairs. Why should we? We pay our council tax just like everyone else in the Borough. I don’t know who signed these works off, but I suggest that if it were their own property they would not have done so; indeed, if the Leader of the Council lived in Slades Drive, it would be a different story. With the above in mind, may I request that a ‘revisit’ be made, with a view to surveying the whole of the pathway, from the junction with Edgehill Rd to the Slades Drive cul-de-sac. The attached photos do not give a full picture. I have others if you would like them.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 13:06, Wed 25 October 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 14:12, Wed 25 October 2023

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 12:16, Fri 8 December 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 12:18, Fri 8 December 2023

  • Curb now dislodged.

    Posted anonymously at 13:30, Wed 27 December 2023

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    State changed to: In progress

    Posted by Bromley Council at 13:43, Thu 28 December 2023

  • Appropriate action has not been taken, indeed it is getting worse. The whole section from the junction with Edgehill toward the junction with the Slades Drive cul-de-sac needs attention, first report refers.

    Posted by Mike Pinchen at 08:31, Wednesday 17 January 2024

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 10:40, Friday 19 January 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 11:22, Thursday 22 February 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 14:04, Thursday 4 April 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 07:34, Friday 24 May 2024

Provide an update