Pothole near middle of the road

Reported via desktop in the Potholes / Highway Condition category anonymously at 22:35, Sat 7 October 2023 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5073080.

There is a pothole that needs filling near the middle of the road.

Due to the location it’s in the normal driving line of cars meaning people swerve to avoid it.

If possible would be good to be repaired in its current state before winter makes it worse.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 22:35, Sat 7 October 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that the carriageway defects meet the investigatory level for repairs and work has been scheduled to resolve them. This should be completed within a 6 month time frame and please be assured that you will receive an update once repairs are concluded.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 11:00, Fri 13 October 2023

  • Can this be repaired at the same time as the other potholes at the top of Bishops Drive which are marked up for repairs (within 28days)?

    The report numbers for the other repairs are:

    5351941 5351933 5351943 5351929 5351926

    Posted anonymously at 22:34, Sunday 14 January 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 22:34, Sunday 14 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and depending on weather conditions we hope for the work to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 11:11, Tuesday 16 January 2024

  • Today (23rd Jan) repairs were done on Bishops Drive yet this has been left.

    Why could this not have been done at the same time as you already had crews working on this road?

    The report numbers for the other repairs were:

    5351941, 5351933, 5351943, 5351929, 5351926

    Please can this be repaired ASAP as it was reported back in October 2023.

    Posted anonymously at 14:16, Tuesday 23 January 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 14:16, Tuesday 23 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and depending on weather conditions we hope for the work to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 13:29, Tuesday 30 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 09:45, Wednesday

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:07, Friday

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by Northamptonshire Highways at 09:14, Friday