Fixed
Multiple deep potholes
Reported via desktop in the Potholes / Highway Condition category anonymously at 09:56, Sun 24 September 2023
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 5025209.
Potholes have formed at the entrance to Moulton College / Moulton Leisure Centre. These are (mainly, but not limited to) in the Westbound direction where vehicles brake and prepare to turn right into the grounds. These have worsened significantly over time to the point where traffic regularly crosses into the oncoming lane to avoid. Urgent repair is required before this causes vehicle damage, or worse, an accident.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 09:56, Sun 24 September 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 28 days. You will receive further information when this job is completed.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by Northamptonshire Highways at 14:02, Tue 26 September 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 08:58, Wed 27 September 2023
-
As well as the potholes in the road the whole boundary between the road and the college driveway has potholes and loose gravel, making it especially difficult for motorcyclists to enter safely.
Posted anonymously at 16:34, Sat 7 October 2023
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by Northamptonshire Highways at 16:34, Sat 7 October 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled - The area has been inspected and work has been scheduled to be carried out within the next 28 days. This will be completed on or before 24th October 2023.You will receive further information when this job is completed.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by Northamptonshire Highways at 11:02, Mon 9 October 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 10:41, Tue 10 October 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 12:12, Tue 10 October 2023
This report is now closed to updates from the public. You can make a new report in the same location.