Reported via desktop in the Road Defect category anonymously at 10:04, Tuesday 12 September 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 4984689.

This pothole on the road near the centre of the roundabout was not fixed when the other potholes nearby were dealt with some months ago!

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 10:04, Tuesday 12 September 2023

  • We have investigated this report and believe no further action is required at this time. The issue may be below our investigatory levels or may no longer be present. If this problem persists, please provide further comments to the report.

    State changed to: No further action

    Posted by Bromley Council at 12:18, Wednesday 13 September 2023

  • The Highway Inspector has raised a job on the roundabout of the Chinese Garage in South Eden Park Road. This is waiting for Traffic Management to allow the contractor to complete the works safely.

    Posted by Bromley Council at 07:37, Thursday 14 September 2023

  • For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake the works.

    State changed to: In progress

    Posted by Bromley Council at 07:38, Thursday 14 September 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 07:41, Thursday 14 September 2023

  • For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake the works.

    Posted by Bromley Council at 11:33, Tuesday 3 October 2023

  • Still open, via questionnaire, 20:13, Tuesday 10 October 2023

  • We are sorry that this work has not yet been completed. We are working with our Minor Works contractor in an effort to resolve this issue.

    Posted by Bromley Council at 13:07, Monday

Provide an update