Tree roots and over hanging brach
Reported via desktop in the Tree roots lifting pavement category anonymously at 10:57, Thursday 10 August 2023 using FixMyStreet Pro
Sent to Bromley Council less than a minute later. FixMyStreet ref: 4877635.
The pavement is very raised now, it is a danger on pavement, it has been marked with white X for about a year, the tree branch overhangs into road over cars, previous workers and cut other branch but keep leaving the one that has been reported
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 10:58, Thursday 10 August 2023
-
The paving slab was adjusted subsequent to when it was marked at the time. The paint will wear away in time. Works have been raised to address the tarmac area over the tree roots where indicated. This report will be referred to the Tree Department in regards to overhanging branches.
Posted by Bromley Council
at 14:11, Thursday 10 August 2023
-
We are continuing to investigate and working to resolve this report
Posted by Bromley Council
at 16:18, Thursday 10 August 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 09:29, Thursday 21 September 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 11:53, Friday 27 October 2023
-
I cannot believe it once again the contractor cut a small branch off and left the large branches over the cars in the road its exactly the same as the picture sent in, and this seems is what they do, everytime, just leave the branch on the left you see in picture, it beggers belief!
Posted anonymously at 13:34, Saturday 28 October 2023
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 09:49, Thursday 2 November 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 12:30, Tuesday
-
Thank you for your comments. The contractor has been instructed to return to site to complete works as specified for the enquiry. Thank you for your continued patience.
Posted by Bromley Council
at 12:30, Tuesday
Provide an update
Your information will only be used in accordance with our privacy policy