Blocked drain outside 42 Ford Street
Reported via desktop in the Blocked/Damaged category anonymously at 10:47, Mon 24 July 2023 using FixMyStreet Pro
Sent to Northamptonshire Highways 1 minute later. FixMyStreet ref: 4818757.
Water not draining - flooding
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 10:47, Mon 24 July 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 28 days. You will receive further information when this job is completed.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 13:12, Mon 31 July 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 14:52, Mon 21 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 18:25, Mon 21 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 20:46, Tue 22 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)
State changed to: In progress
Posted by Northamptonshire Highways at 18:49, Wed 30 August 2023
-
Still blocked and flooding 13/10/23
Posted anonymously at 18:00, Fri 13 October 2023
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by Northamptonshire Highways at 18:00, Fri 13 October 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed) - The area has been inspected and work has been scheduled to be carried out within the next 28 days. You will receive further information when this job is completed.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 10:25, Thu 19 October 2023
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by Northamptonshire Highways at 14:30, Tuesday 23 January 2024
This report is now closed to updates from the public. You can make a new report in the same location.