Kerb/gutter breaking up beside Green Street Green Mini-Roundabout

Reported via desktop in the Road Defect category by Friends of Green Street Green at 09:19, Saturday 8 July 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 4762873.

Fri 30 Jun 2023: Please repair damage to footway kerb and road gutter at the mini-roundabout collision hotspot. TIA

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 09:19, Saturday 8 July 2023

  • We are continuing to investigate and working to resolve this report

    Posted by Bromley Council at 09:06, Monday 10 July 2023

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 15:08, Friday 14 July 2023

  • We are continuing to investigate and working to resolve this report

    Posted by Bromley Council at 13:19, Friday 21 July 2023

  • For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake the works.

    Posted by Bromley Council at 10:42, Friday 4 August 2023

  • Thank you for your further comments regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.

    Posted by Bromley Council at 13:11, Friday 13 October 2023

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 12:07, Tuesday 24 October 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 07:51, Wednesday 25 October 2023

  • Thanks for completing repair within four months.

    Posted by Friends of Green Street Green at 12:46, Wednesday 22 November 2023

Provide an update