Path cracking up

Reported via iOS in the Pavement Defect category by dan marsh at 21:02, Monday 12 June 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 4663719.

Widmore rd / market square traffic lights Outside ocean basket.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 21:03, Monday 12 June 2023

  • We have investigated this report and found it to be the responsibility of British Telecom. We have therefore referred the enquiry to British Telecom. Future issues with BT infrastructure can be reported direct to BT via their subsidiary Openreach: https://www.openreach.com/ help-and-support/ damage-health-and-safety

    State changed to: third party responsibility

    Posted by Bromley Council at 15:58, Tuesday 13 June 2023

  • Further works are necessary to resolve the issue and have been scheduled for action.

    State changed to: In progress

    Posted by Bromley Council at 14:50, Wednesday 14 June 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 15:25, Wednesday 14 June 2023

  • Hi which update is correct please?

    State changed to: Open

    Posted by dan marsh at 16:01, Wednesday 14 June 2023

  • As expected!

    Posted by dan marsh at 19:09, Wednesday 14 June 2023

  • This defect has been passed back to the contractor who did the work originally and we are waiting for a start date to rectify this problem.

    State changed to: Closed

    Posted by Bromley Council at 15:41, Wednesday 21 June 2023

  • This defect has been passed back to the contractor who did the work originally and we are waiting for a start date to rectify this problem.

    Posted by Bromley Council at 15:41, Wednesday 21 June 2023

  • This defect has been passed back to the contractor who did the work originally and we are waiting for a start date to rectify this problem.

    Posted by Bromley Council at 15:41, Wednesday 21 June 2023

  • Open untill fixed

    State changed to: Open

    Posted by dan marsh at 17:44, Wednesday 21 June 2023

  • Still open, via questionnaire, 22:00, Monday 10 July 2023

  • Nothing done. Getting worse

    Posted by dan marsh at 15:07, Sunday 6 August 2023

  • This defect has been passed back to the contractor who did the work originally and we are waiting for a start date to rectify this problem.

    Posted by Bromley Council at 08:25, Friday 18 August 2023

  • This defect has been passed back to the contractor who did the work originally and we are waiting for a start date to rectify this problem.

    State changed to: Closed

    Posted by Bromley Council at 10:10, Wednesday 11 October 2023

  • Nothing done

    State changed to: Open

    Posted by Dan Watson-marsh at 12:50, Saturday 28 October 2023

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you

Your update

Tell us about you