Pothole in centre of road
Reported via mobile in the Potholes / Highway Condition category anonymously at 10:17, Sun 28 May 2023
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 4604229.
This pothole has increased in size over last few weeks. Drivers are avoiding it by driving on opposite of road, also on a ‘blind’ bend so an accident waiting to happen.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 10:18, Sun 28 May 2023
-
Investigation: Completed (Defect Found) - The area has been inspected and work have been scheduled to be carried out within the next 26 weeks
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 14:24, Mon 5 June 2023
-
Not getting any smaller !
Posted anonymously at 06:10, Mon 26 June 2023
-
Not getting any smaller !
Posted anonymously at 06:10, Mon 26 June 2023
Still open, via questionnaire -
Hopefully that repair is temporary, or is this the standard of work the council accept on behalf of council tax payers.
Posted anonymously at 09:24, Mon 24 July 2023
-
Hopefully that repair is temporary, or is this the standard of work the council accept on behalf of council tax payers.
Posted anonymously at 10:22, Mon 24 July 2023
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by Northamptonshire Highways at 10:48, Mon 24 July 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and temporary work has been put in place the permanent work has been scheduled to be carried out within the next 26 weeks
Posted by Northamptonshire Highways at 09:49, Tue 25 July 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 06:50, Wed 2 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 11:20, Thu 3 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 11:46, Thu 3 August 2023
This report is now closed to updates from the public. You can make a new report in the same location.