The path all along Slades drive on the right hand side with the meadow on the right has been repeatedly driven over and has crumbled away.
Reported via iOS in the Pavement Defect category anonymously at 16:11, Tue 25 April 2023
Sent to Bromley Council less than a minute later. FixMyStreet ref: 4485021.
Deteriorating pathway and kerb along the right hand side of Slades drive. It has been repeatedly driven over by trucks whilst building the new school.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council at 16:11, Tue 25 April 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council at 13:23, Thu 27 April 2023
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 11:20, Tue 23 May 2023
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 11:21, Tue 4 July 2023
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council at 08:34, Wed 26 July 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council at 11:01, Fri 11 August 2023
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council at 07:39, Thu 7 September 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council at 12:16, Sat 16 September 2023
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council at 14:09, Wed 25 October 2023
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 11:14, Wed 6 December 2023
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 12:16, Thursday 4 January 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 12:37, Wednesday 10 January 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 09:57, Wednesday 17 January 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 13:00, Tuesday 23 January 2024
-
Thank you for your report, Bromley are aware of the volume of works outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our officers our not able to give precise timeframes to individual jobs at this moment but we are continuing to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able. The area will guarded until a full repair can be achieved. I would like to apologise on behalf on the London Borough Of Bromley and our contractor and any inconvenience caused by this matter.
Posted by Bromley Council at 13:09, Thursday 25 January 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 11:32, Thursday 22 February 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Posted by Bromley Council at 10:37, Tuesday 19 March 2024
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council at 11:37, Tuesday 19 March 2024
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council at 14:08, Monday