Fixed
Mini roundabout in need of repair
Reported via Android in the Road Defect category anonymously at 10:59, Tue 18 April 2023
Sent to Bromley Council less than a minute later. FixMyStreet ref: 4455223.
At junction of Homefield Rise and High Street
Asset ID: FP193
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council at 10:59, Tue 18 April 2023
-
Large chucks of mini roundabout missing
Posted anonymously at 14:09, Tue 18 April 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council at 08:24, Mon 24 April 2023
-
Can they be asked to make a more lasting repair please this time around?
Posted anonymously at 19:33, Mon 24 April 2023
-
Large chunks of mini roundabout are missing and bricks are damaged. Can we have a more lasting solution please? As the last temporary fix failed? Thanks
Posted anonymously at 19:15, Mon 8 May 2023
-
Not fixed
Posted anonymously at 17:03, Tue 16 May 2023
Still open, via questionnaire -
Possibly a temporary fix only
Posted anonymously at 20:39, Tue 13 June 2023
Still open, via questionnaire -
Not fixed properly
Posted anonymously at 21:56, Tue 11 July 2023
Still open, via questionnaire -
This repair has not yet been carried out, temporary repairs have been completed to keep the area serviceable until works can be completed. Thank you for your patience in the meantime.
Posted by Bromley Council at 10:14, Mon 24 July 2023
-
When will it be fixed properly please?
Posted anonymously at 22:46, Tue 8 August 2023
Still open, via questionnaire -
Still waiting for lasting repair
Posted anonymously at 08:03, Wed 6 September 2023
Still open, via questionnaire -
This repair remains outstanding with our contractor and has been programmed for completion by the end of week commencing 11/09. Thank you for your patience in the meantime.
Posted by Bromley Council at 16:08, Wed 6 September 2023
-
Thanks for the update and indication of a completion date. Much appreciated.
Posted anonymously at 17:35, Wed 6 September 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council at 13:21, Mon 11 September 2023
-
Further works are necessary to resolve the issue and have been scheduled for action.
State changed to: In progress
Posted by Bromley Council at 09:26, Fri 15 September 2023
-
When will this work commence please? Thanks
Posted anonymously at 12:02, Fri 15 September 2023
-
Resurfacing was completed 07/09, 8 days prior to your last comment. Finalising of these works has been scheduled with our contractor.
Posted by Bromley Council at 10:44, Tue 19 September 2023
-
Still ongoing
Posted anonymously at 10:51, Wed 4 October 2023
Still open, via questionnaire -
Still open, via questionnaire, 11:07, Wed 1 November 2023
-
These works are now complete. Thank you for using Fix My Street.
State changed to: Fixed
Posted by Bromley Council at 09:46, Fri 10 November 2023
-
Thank you for using FixMyStreet to report your concerns to Bromley.
Posted by Bromley Council at 09:49, Fri 10 November 2023
-
Appropriate action has been taken to resolve the issue.
Posted by Bromley Council at 11:13, Fri 24 November 2023
This report is now closed to updates from the public. You can make a new report in the same location.