Fixed
Very wide pothole at top of Shelley drive near junction with Northampton road
Reported via mobile in the Potholes / Highway Condition category anonymously at 15:00, Tue 11 April 2023 using FixMyStreet Pro
Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 4425374.
Been here over a month and incorrectly stated as repaired on this website
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 15:00, Tue 11 April 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Shelley Drive, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by Northamptonshire Highways at 14:32, Thu 13 April 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 12:20, Thu 31 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 12:02, Mon 4 September 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 12:19, Mon 4 September 2023
This report is now closed to updates from the public. You can make a new report in the same location.