Permanent large puddle every time it rains

Reported via mobile in the Road Defect category anonymously at 16:00, Thu 9 March 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 4295741.

Afrer major work last year to remodel the Hayes St / Pickhurst Lane roundabout, this large puddle appears and does not drain away. Inconveniencing pedestrians with vehicle road spray every time a vehicle goes by.This puddle is also in the middle of the main pedestrian crossing point. This is unacceptable after the time and money spent on this remodelling work last year.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 16:01, Thu 9 March 2023

  • We are continuing to investigate and working to resolve this report

    Posted by Bromley Council at 10:59, Mon 27 March 2023

  • Still open, via questionnaire, 11:45, Sat 8 April 2023

  • Still open, via questionnaire, 14:40, Mon 8 May 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 12:42, Mon 15 May 2023

  • We apologises for lack of update regarding this enquiry. Our contractor is aware of the ponding at this location and are looking at options to alleviate the issue. Unfortunately we don't have a programme date for these works but we will continue to chase them and provide an update shortly.

    Posted by Bromley Council at 12:21, Mon 21 August 2023

  • Bromley Council are aware of the issues at this location. This road has already been included in the Council's schedule of major highway maintenance works programme. In the interim the condition of the highway will continue to receive regular safety inspections and any necessary work undertaken accordingly, specific issues in the road should be reported with location details as new reports via https://fix.bromley.gov.uk for investigation.

    State changed to: No further action

    Posted by Bromley Council at 12:37, Mon 21 August 2023

This report is now closed to updates from the public. You can make a new report in the same location.