Reported via mobile in the Road Markings - Worn/Faded category anonymously at 18:11, Wed 8 March 2023 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 4293276.

Was told 2 months ago this would be followed up on but heard nothing.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 18:12, Wed 8 March 2023

  • Investigation: Ongoing - We can confirm that this issue will be investigated within a weeks' time and we will update you accordingly.

    Posted by Northamptonshire Highways at 14:38, Wed 15 March 2023

  • Another month and still no update?

    Posted anonymously at 19:16, Thu 13 April 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Hawthorn Road, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.

    Posted by Northamptonshire Highways at 14:02, Thu 25 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 16:00, Tue 17 October 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 11:02, Wed 18 October 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 11:25, Wed 18 October 2023

This report is now closed to updates from the public. You can make a new report in the same location.