Tripping hazard from recently replaced paving around 80 St James's avenue

Reported via mobile in the Pavement Defect category anonymously at 06:31, Tue 7 March 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 4288205.

There is a recently replaced paving around 80 St James avenue which is very uneven. It is pink in colour and has cutout in one corner making L shape in appearance. It has been laid very uneven and corner is high enough to be a tripping hazard.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 06:32, Tue 7 March 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 08:26, Tue 14 March 2023

  • Still open, via questionnaire, 07:02, Tue 4 April 2023

  • We are working with our Minor Works contractor to ensure this work is completed. Thank you for your patience.

    Posted by Bromley Council at 18:57, Thu 20 April 2023

  • Not fixed

    Posted anonymously at 08:12, Tue 2 May 2023
    Still open, via questionnaire

  • We are sorry that this work has not yet been completed. We are working with our Minor Works contractor in an effort to resolve this issue.

    Posted by Bromley Council at 12:47, Thu 11 May 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 12:55, Tue 16 May 2023

  • Still open, via questionnaire, 08:31, Tue 30 May 2023

  • Paving is no longer creating a tripping hazard but is now broken onto two pieces

    State changed to: Open

    Posted anonymously at 08:32, Tue 30 May 2023

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 11:07, Wed 31 May 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 15:20, Thu 1 June 2023

  • Thank you for your patience. Our contractor is due to return shortly to carry out this repair.

    Posted by Bromley Council at 10:44, Tue 25 July 2023

  • We are sorry that this work has not yet been completed. We are working with our Minor Works contractor in an effort to resolve this issue.

    Posted by Bromley Council at 19:08, Mon 18 September 2023

  • We are aware this has not yet been completed and we are working with our contractor to complete this asap. Thank you for your patience.

    Posted by Bromley Council at 11:21, Mon 6 November 2023

  • Please bear with us. These works are still outstanding with our Minor Works contractor and will be completed soon.

    Posted by Bromley Council at 11:52, Thu 16 November 2023

  • We are sorry that this work has not yet been completed. We are working with our Minor Works contractor in an effort to resolve this issue.

    Posted by Bromley Council at 11:52, Fri 24 November 2023

  • Our contractor is aware of this outstanding work and it will be completed shortly. Thank you for your patience.

    Posted by Bromley Council at 11:24, Thu 30 November 2023

  • We are aware of these outstanding works and we are working with our contractor to ensure completion. Thank you for your patience.

    Posted by Bromley Council at 12:23, Thu 7 December 2023

  • Our contractor is aware this work is outstanding. We are working with him to ensure this work is completed. Thank you for your patience.

    Posted by Bromley Council at 12:04, Thu 14 December 2023

  • We are working with our contractor to ensure these works get completed soon. Thank you for your patience.

    Posted by Bromley Council at 11:11, Thu 21 December 2023

  • Our contractor has been instructed to complete these works as soon as possible. Thank you for your patience.

    Posted by Bromley Council at 11:00, Thursday 4 January 2024

  • Our contractor is aware that this work is outstanding. We are working with him to ensure this is completed shortly. Thank you for your patience.

    Posted by Bromley Council at 11:24, Thursday 11 January 2024

  • The issue has been re-attended and additional works completed. If the issue re-occurs please re-report via: https://fix.bromley.gov.uk

    State changed to: Fixed

    Posted by Bromley Council at 11:54, Thursday 25 January 2024

This report is now closed to updates from the public. You can make a new report in the same location.